» The procedure for transferring construction readiness for installation of APS. The composition of the executive documentation under the section "Fire alarm" (PS)

The procedure for transferring construction readiness for installation of APS. The composition of the executive documentation under the section "Fire alarm" (PS)

Quoting of dear Volzaninin. Gold Edition.
Part 941.

SNIP 12-01-2004 Construction Organization
Snip 3.01.01-85
GOST R 54101 2010
Snip 3.01.04-87 Acceptance of the completed construction of facilities.
RD-11-02-2006 Composition and procedure for conducting executive documentation


BCH 25-09.67-85 "Rules of production and acceptance of work. Automatic fire extinguishing installations"
Guidelines " Automatic systems fire extinguishing I. fire alarm. Acceptance and Control Rules
RD 78.145 -93
It is necessary to distinguish:
- valid documentation that is underway during the installation process;
- valid documentation, which is issued when commissioning the installation;
--Technical documentation that should be stored at the facility and in the process of operation of the installation. The composition of this operational documentation includes performing documentation.

Executive documentation, which is maintained during the installation process:
SNiP 3.01.01-85 "Organization of construction production"
paragraph 1.14 Executive Documentation - a set of work drawings with inscriptions on the conformity of work done in nature by these drawings or in them as appropriate with the project organization made by persons responsible for the production of construction mounting work.
SNiP 3.05.06-85
p. 1.7. On each object of construction, in the process of installing electrical devices, special magazine production of electrical installation works should be conducted according to SNiP 3.01.01-85, and upon completion of the work, the electrical installation is obliged to transfer the documentation to the General Contractor for the Working Commission according to SNIP III-3-81. The list of acts and protocols of inspections and tests is determined by the INT, approved in the planned SNiP 1.01.01-82.
SNIP 12-01-2004 "Construction Organization"
5.14 The performer works executive documentation:
- a set of work drawings with inscriptions on the circumference of the works made in the nature of these drawings or about the changes made in them in coordination with the designer made by persons responsible for the production of construction and installation work;

3. Executive documentation is text and graphic materials reflecting the actual execution of design solutions and the actual position of capital construction objects and their elements in the construction process, reconstruction, overhaul Capital construction facilities as the work of work defined in the project-needed documentation.

Executive documentation, which is issued when the installation acceptance is commissioned
Snip 3.01.04-87 Acceptance of the completed construction of facilities. Basic provisions.
3.5. The general contractor presents the working commissions of the following documentation:
b) A set of work drawings for the construction of an object developed by design organizations, with inscriptions of the works carried out in nature, these drawings or amendments made in them made by Li Cami, responsible for the production of construction and installation work. The specified set of work drawings is the executive documentation;
VNC 123-90 "Instructions for registration of acceptance and delivery documentation for electrical work"
Executive documentation - part (section) "Vedomosti technical documentation that is submitted during the acceptance of electronic tromontal work."
GOST R 50776-95
3.2 Work planning
Performed works on ... Installation and operation of the STS ... should be planned taking into account the following standard list of stages:
…………..
l) verification and delivery of the established STS into operation with a set of working documentation for operation and maintenance.
BCH 25-09.67-85 "Production and acceptance rules. Automatic fire extinguishing installations" and
Methodical recommendations "Automatic fire extinguishing systems and fire alarms. Rules of acceptance and control"
13.5. When accepting the AUP commissioning, assembly and commissioning organizations must present:
- executive documentation (a set of work drawings with changes made in them);

Technical documentation that should be stored and carried out during the operation of the installation.
Rules of fire fighting regime in the Russian Federation
61 .... The object should be kept executive documentation for installation and system fire protection object.
RD 009-01-96
1.5 General requirements for technical documentation.
1.5.1 At the facility that operates the installation of fire automation must be the following documentation:
a) design and estimate documentation (act of examination);
b) performing documentation and schemes, acts of hidden work (if available), tests and measurements;
………
P)…



Here the phrase is "project documentation and executive drawings for installation" - very not exact.

Operating documents - according to GOST 2.601;

JV "Fireman technique. AUPC and PT. Requirements for installation and operation" - a project and referred to it early.

RD 11-02-2006 "Composition and procedure for conducting executive documentation"
3. Executive documentation is text and graphic materials reflecting the actual design of project decisions and the actual position of capital construction objects and their elements in the construction process, reconstruction, overhaul of capital construction facilities as the work of the work defined in the project.
p. 5. Executive documentation is conducted by the construction of construction.

After all, no one argues that the executive documentation \u003d is conducted \u003d on the installation.
Nobody doubts that the installation of strictly (strictly) on the project is not realistic. Be sure to retreat. For example, in trace cable lines, in the actual location of detectors and other ...
Although the word \u003d retreat \u003d somewhat dangerous, it will attract coordination with the designer (if it is not proper).
It is necessary to say "softer" - some minor inaccuracies.
Smoker.
If you conducted the executive documentation in fact, and was correct, then after passing the object, why do you need this waste paper?
So give it to the customer.
And the executive documentation is not only the schemes that require you. So the customer will need to be very easy to pick up you all. (See SNiP 3.05.06-85, p. 1.7).
And B.
VNC 123-90 "Instructions for registration of acceptance and delivery documentation for electrical work"

As usual competently told in
"Fire safety rules for Moscow"
3.1.14. At the facility at the person responsible for the operation of the installation, the following technical document of the installation should be available:
a) project documentation and executive drawings for installation;

Although here the phrase is "project documentation and executive drawings for installation" - very not accurate.

By the way, not so long ago disassembled the question of whether the project was needed on commissioned?
I will not bother you, but the point is that the project (more precisely - working documentation) is needed only for Montnikov, and the owner of the object after putting into operation it is the executive documentation.

The main regulatory message:
PPB01-03 P.98. Fire automation installations must be in good condition and constant readiness, match project documentation.

FZ "Trotpb" No. 123 Article.83 Part 1. The automatic installations of fire extinguishing and fire alarms should be mounted in buildings, structures and buildings in accordance with the design documentation developed and approved in the prescribed manner.

SNIP 21-01-97 "Fire safety of buildings and structures"
Clause 4.3 ... prevent changes in constructive, volume-planning and engineering technical solutions Without a project developed in accordance with applicable norms and approved in the prescribed manner. "

RD 78.145-93 Systems and Complexes of the Security, Fire and Security and Fire Alarm. Rules of production and acceptance of work
p.1.1. Installation work on the installation of technical alarms should be carried out in accordance with the approved design and estimate documentation or an act of examination (in accordance with model project decisions), working documentation (project manufacturing project, technical documentation of enterprises - manufacturers, technological maps) and these Rules.

VNG 25 - 09.67 - 85 "Rules of production and acceptance of work.
Automatic fire extinguishing installations »
1.1. Work on the installation of automatic fire extinguishing installations should be carried out in accordance with the approved design and estimate and working documentation, project manufacturing project (PPR) and technical documentation of manufacturers.

"Fire safety rules for Moscow"
3.1.1. Installations of the EPS must comply with the technical solutions and requirements of the project. The introduction of any changes to the design of the installation, reproduction of protected premises and other reorganization is allowed to be made in agreement with the project organization, which informs the state authorities fire service (GPS).
3.1.14. At the facility at the person responsible for the operation of the installation, the following technical documentation should be available:
a) project documentation and executive drawings for installation;

Article 83. Requirements for systems automatic fire extinguishing and fire alarm systems

1. Automatic fire extinguishing and fire alarm systems must be mounted in buildings, structures and buildings in accordance with the design documentation developed and approved in the prescribed manner.

Hello everyone, friends! Vladimir Raichiv, decided to offer you another topic for discussion. The fact is that I have no executive documentation on the APS system and it is terrible. It is necessary to do, I think that by the new year I will try to knock the money from the manager to this case.

One of the important documents at any enterprise is the "Fire alarm project and system alert systems about the fire in the premises" (hereinafter - "APS project"). It is based on the installation of technical equipment APS, as well as planning and calculation maintenance. This article will disclose the main features of the process called the design of the fire alarm.

In any work associated with fire safety, the key point is to comply with certain prescriptions approved by the country's legislative authorities.

What are the standards for design an APS?

The main standards governing the composition and principles of creating AUPC systems in protected premises are:

It is worth noting that for each category of buildings (administrative and domestic, warehouse, manufacturing buildings) there are arms of the rules that have completed above.

The following regulatory documents are displayed direct requirements for design and filling the project:


What does the Writing of the "APS project begins"?

Any project work begins with the collection of source data. In the case of AUPC, the key issues during the object examination are:

  1. Volume and planning solutions (the presence of columns, beams, wall thickness, coatings and overlaps);
  2. Decorative and finishing materials of walls, floors, ceilings;
  3. Functional purpose of protected premises, features of processes occurring in the premises;
  4. Number of jobs (in some cases).

These initial data should provide a customer organization. Otherwise, the project organization will have to examine the object, which will affect the cost of project development.

What is the cost of designing PS?

The very question for which you call the design complex for the sake of which. For this purpose, the estimate is calculated for the design, which determines the cost of each type of work. It is worth noting that it does not affect her the number of protected premises constituting the object.

Then what increases the cost of the project?

First, the total area of \u200b\u200bthe premises and the area of \u200b\u200browers and (or) of the rafts in these premises, which is written by the project. Secondly, the features of the equipment intended to the "technical task for design" (hereinafter referred to as TK). Thirdly, complicating the features of the premises (for example, they belong to the objects of special purpose or historical or cultural value). Fourth, interaction with technological installations available on the object.

It is worth noting that some organizations can count the cost design work Not according to specialized sets of rates, but asking a certain percentage of the estimates on the installation of equipment (if the contract with these organizations is to create a project, and on the installation of alarm).

Who can do the design of AUPC?

The design of fire safety systems in general (and alarm component in particular) is the type of work involving licensing of the executive company (only now it is not a MOE license, but membership in SRO). The admission of SRO is the same document that confirms the right to organize the exquisition work in the design of AUPC and other related systems.

The composition of the project documentation

It would seem that the project documentation should always be the same in composition, but even here there are a certain kind of variation of the composition of documents. Most often, project organizations offer two types of documents - a working draft (RP) or working documentation (RD).

What is the fundamental difference between these two concepts?

Secret lies in an explanatory note. Working documentation contains only short description object I. decisions taken (or does not have an explanatory part at all).

The next question immediately suggests - what documents are in the aggregate of RP? Below will be a list-content of the most commonly found as part of the RP of documents.

  1. Licenses of the project organization.
  2. Technical task for design.
  3. Initial data on design.
  4. Explanatory note.
  5. The main set of drawings.
    1. Legend.
    2. The location of the technical means of the APS (floor plans).
    3. Functional scheme for connecting technical means.
    4. Features of the installation of detectors (optional drawing).
  6. Tasks organization-customer.
  7. Hardware Specification.
  8. Certificates for used equipment.

Key features of the explanatory note

  • description of the protected APS object;
  • justification of the accepted technical solutions;
  • calculation of AUPC power.

Why are they key?

Depending on the type of object, its functional purpose and architectural features, regulatory documents may vary the composition of the technical means of the APS. For example, within the framework of the finishing features of the monasteries and temples, it is impossible to use wired detectors in the melon races with extractive painting on the walls.

What is important to substantiate the adopted technical solutions? Based on the Specification of the Equipment to the "project of the APS", the installation organizations will compile estimated documentation for the installation of APS. And focusing on the rationale for the process, the specialists of this company will be able to pick up suitable analogs of equipment in case of their disappearance from the market.

Calculation of CAUPS is important for right choice A backup power supply - according to AUPS standards, it should work within 24 hours of autonomous regime and 3 hours in the "fire" state. Also, the calculation of nutrition allows you to learn the maximum current consumption of the entire system, which affects the possible need to use additional reserve sources Nutrition.

Why do I need certificates for equipment?

In the absence of a certificate certificate certificate fire safety The device and (or) of the detector, this equipment cannot be used in AUU.

And in this video, an overview of the project documentation is made on the example apartment house:

Well, friends, I think I managed to consider the issue of design an APS as much as possible. For myself, I understood which sections it is desirable to have in executive documentation. And I briefly say goodbye to you, subscribe to blog news, share interesting articles on social networks, to new meetings, for now.

1. Register of executive documentation

2. General Journal of Work and Special Works:

  • Cable laying log
  • Input control log
  • Journal of the author's supervision (filled with a responsible person from the project organization)

3.

  • Executive Fire Alarm System

4. Acts, Acceptance and Test Protocols, Other Documents:

  • Act of the transfer of equipment, products and materials in installation
  • The act of examination of the building (object name, number of buildings, premises, floors, type of structure, indication of the type of signaling, type of detectors, receiving and control devices, alarms and places of their installation for each building (premises), indication of blocking building structures (material name, size, number of protected structures, type and number of detectors), indication of the length, types of laying of wires and their protection, indication of power supply, estimated value and planned on installation, signatures of customer representatives, security divisions, state fire supervision bodies ).
  • Act of the readiness of buildings and structures to the work of work
  • Act on the end of work
  • MEASURING MEASUREMENT MEASUREMENT MEASUREMENTS
  • Vedency mounted PCP (SPU) and detectors
  • Act of testing of protective pipelines with separation seals for tightness (compiled when installing technical means of alarm in explosive zones)
  • The statement of technical documentation presented during acceptance
  • Statement of mounted equipment
  • Statement of changes and retreats from the project
  • Insulation resistance measurement protocol
  • Act technical readiness system

5.

  • Laying fire alarm networks (walls, ceilings, in floor, sewage, land)

6., Firefighters certificates, sanitary and hygienic conclusions on construction Materials, products and designs. Building materials, products, designs and equipment arriving at the construction site, the act of input control must be drawn up with the subsequent signing by its responsible persons.

7. A set of work drawings for the construction of an object developed by project organizations, with inscriptions on the conformity of the work carried out in nature, these drawings or amendments made in them made by persons responsible for the production of construction and installation works agreed with the project authors.

8. Documents on the coordination of retreats from the project during construction


The reception documentation includes a package of permits:

  • Information sheet of the assembly organization
  • SRO Mounting Organization
  • Orders for responsible representatives
  • Certificates of personnel (welders, electrotechnical personnel, etc.)
  • Working documentation with a customer stamp "In the work of work"
  • Project manufacturing work (title list and review list)

* The presented composition of the executive documentation is approximate. Specify the exact composition of the executive documentation from the customer.


Fire alarm executive documentation

IN fire alarm executive documentation A set of work drawings and text documents that facilitate the process of operation of the building are facilitated. It must be provided by the Ministry of Emergency Situations conducted by checking on the first requirement. The presence of a fire alarm id helps to avoid problems with the law.
If the executive documentation for the APS (OPS) and SOUE is lost or not made by those who made the installation, it must be restored.

Stages of recovery of executive documentation for fire alarm

To start working on the recovery of documentation, plans for the building from the technical inventory bureau (BTI plans) are needed.

BTI plans look like this:

The plan is crossed for AutoCAD in editable format.dwg

Then the automatic fire alarm system is then examined. The presence, location, quantity and type of sensors, devices and modules, of which it consists is checked. The data obtained is applied to measurement drawings.

Photograph receiving-control devices,

hand and smoke detectors.

It is also important to the distribution of fire alarm loops by premises.

After the survey, you can proceed to draw executive documentation for fire alarm.

This stage is similar to design, but with the already finished placement that is required to be transferred to the plan for cable tracks.

Example of a plan of the executive scheme for the arrangement of fire detectors:

Cost of executive documentation on an APS

To determine the cost, a technical passport of the building or BTI plans is necessary. The calculation is made taking into account the area of \u200b\u200bthe object, but The cost of developing executive documentation depends on many factors. Each order is individual.

Send to the mail that is specified in the Contacts section, the source data. We will make a calculation as soon as possible and send it to you.

The standard date of execution of the IDC to 2000m2 is 7-10 days. The price includes an object examination, the creation of documentation and the transfer of two paper copies to the client.

Reduce the cost of execution of work (relevant for service organizations and companies with design skills) in two ways:

  1. Purchase an example of a project in editable format (DWG, DOC). This project you independently lend to your layouts. This option is possible only in the presence of a project SRO. Composition of documentation: title, cover, explanatory note, general data, conditional notation, structural scheme, Equipment Plans and Cable Trails, Connection Schemes, Cable Journal, Specification.
  2. Pay for remote support for your project. You collect all the source data (plans, location, detectors and appliances), we produce a normocontrol project.

Call the phone indicated on the site, and our manager will select the optimal option for you, which will help to save significantly.

Fire alarm means are a complex complex of equipment, controllers and sensors. This is one of the main engineering systems Buildings responsible for the safety of people, personnel and visitors. When creating an APS system, executive documentation of the fire alarm project is compiled. Depending on the features of objects, the project will be different, and the composition of the executive fire alarm documentation, which is governed by a special rule, IVC 25-09,67-85, as well as the RD 78.145-93 - a guidance document regulating the rules of work when creating an APS.

The last standard gives the definition of the term ID. In paragraph 11.4, it is written that the assembly organization, which implemented the draft fire equipment system should be submitted to the Commission;

  • Working documentation - a set of drawings or acts of surveys;
  • TD from manufacturers' factories;
  • Certificates of conformity, technical passports;
  • Production documents. "

Another norm known to all the leaders of the Fire Regime Rules Russian Federation in paragraph 61 of which it is indicated that all technical documents According to the PS constitutes a contractor, an organization that performs installation operations in the building or in the territory, and when surrendering transfers to customers. Documents are stored by the client and are presented at the request of the MES inspectors.

Why do we trust the creation of the IDP?

When working on the design and creation of fire protection, Gefest Alarm LLC makes up and transfers the customer all the drawings, schemes, acts that fully comply with state regulations and regulations. But on other objects, it can be lost or drawn up with errors, which will cause claims from inspection bodies. In this case, you can contact our experts for the recovery service. This is a complex process that is similar to design.

We will conduct a full examination of the equipment, we will make plans and create drawings of cable communications. To carry out these works, we will need a building plans, all other papers, certificates and acts related to the current PS.

  • Events on the preparation or recovery will be carried out at the highest level.
  • We guarantee high quality of these works, we have great design and implementation of APS systems.
  • All operations are performed in accordance with the requirements of the PPR and RD.

We can also make a ID for mounting organizations, it will free their time and resources, will provide an opportunity to focus on the facility and be sure that all the papers will be ready on time.

The composition of the executive documentation

The list of executive documentation for fire alarm on the RD 78.145-93 is shown below.

1. Magazines

  • General Journal of Works;
  • Input control log;

2. Executive schemes

  • Executive drawing of fire alarm networks;

3. Acts of examination of hidden work:

  • Laying fire alarm networks (walls, ceilings, in the floor; sewage; in the ground);

4. Test acts and statements:

  • Acts of input control;
  • Act of the transfer of equipment, products and materials in installation;
  • Act of the building survey;
  • The act of readiness of buildings and structures to the production of installation work;
  • Protocol measurement of electrical wiring insulation resistance;
  • Act on the end of the installation work;
  • Statement of mounted PCP (SPU) and detectors;
  • The act of testing of protective pipelines with separation seals for tightness (is compiled when installing the technical means of alarm in explosive zones);
  • Act on completion of commissioning;
  • Act of comprehensive tests automatic installation fire alarm;
  • Act of acceptance of technical means alerts and manage the evacuation of people in order to operate after comprehensive testing;
  • Act of acceptance of technical means of fire alarm operation;

5. Quality certificates and passports for applied materials and equipment, sanitary-epidemiological conclusions, fire safety certificates;